Panhandle Bike Ranch vs. Bonner County: A Timeline

Panhandle Bike Ranch — the story so far

A timeline of building the park, the CUP being vacated, the transition to a nonprofit, and the ongoing fight with Bonner County

Years of work, opening within reach
Building Panhandle Bike Ranch

Several million dollars invested in 8+ miles of trails, parking, well, septic, and a welcome center on 170 acres in Sagle. The county had approved the conditional use permit twice.

June 3, 2025
CUP vacated, sent back to the county

The judge's ruling was about the county's process, not anything PBR did wrong: Bonner County failed to properly document its findings of fact on why it had approved the recreation facility. The permit was vacated and remanded on that procedural failure alone — right as the park was ready to open, after two prior approvals.

July 8, 2025
Meeting with Bonner County planning

Attorneys asked the county to simply fix the findings of fact — all the judge had actually asked for — but the county refused, saying the commissioners wanted a whole new hearing from scratch. County planning staff floated the idea directly: operating on a donation basis wouldn't require a CUP, as long as no donation or payment was required to ride.

July 19, 2025
Donation-based operations begin

Started operating on a donation basis, directly following the guidance given by Bonner County planning.

August 5, 2025
Violation notice over website wording

The county flagged a word on the website implying donations were required. Fixed immediately and sent evidence back asking the county to confirm the issue was resolved — they never responded, and no further violations followed for 10 months.

Summer 2025 – early 2026
Transition to a nonprofit, donation-based model

The nonprofit path felt right — community feedback from events kept pointing that way, and PBR had essentially been operating like a nonprofit since day one: free to the public at first, then on a donation basis. Formed PBR Inc. as a 501(c)(3), with PGS LLC leasing the land to it, filed Form 1023, and stood up formal governance to match.

September 12, 2025
Formal park designation letter sent

Attorneys sent Bonner County a formal letter requesting PBR be recognized as a park under county code, following up on planning staff's own guidance about the donation-based path. BCRC § 12-816 defines a "Park" as "a noncommercial facility designed to serve the recreational needs of the residents of the community" — the definition the letter argued PBR meets.

September 23, 2025
Building location permit submitted

Applied for an accessory building permit for a welcome center and bathrooms, meant to put to use the public well and septic system the earlier CUP approvals had already required — and that significant time and money had already gone into building.

October 15, 2025
County denies the park designation

Alex Feyen responded on behalf of the county, denying park status and classifying PBR as a recreation facility — the county's position being that nonprofit status didn't matter because it still viewed the operation as commercial activity.

October 24, 2025
Appeal filed with the county commissioners

Attorneys sent a letter to the Bonner County commissioners asking them to appeal interim planning director Alex Feyen's park designation determination.

November 5, 2025
County says the decision isn't appealable

Feyen forwarded a response from Deputy Prosecutor Nate Adams: while county code generally allows appeals of planning director decisions to the Board, he argued specific carve-outs make the director's use-table interpretations and zoning classifications final and not appealable.

November 13, 2025
Building permit denied

The county denied the BLP, reasoning that the vacated CUP meant no commercial use — including the welcome center and bathrooms — could be permitted. The catch: the planning department itself had earlier told the engineering firm to classify the structure as commercial for billing purposes, since it fit no other category, then used that same classification to deny the permit.

December 4, 2025
BLP denial appealed to commissioners

Givens Pursley appealed the BLP denial, arguing PBR meets the code's definition of a noncommercial "Park," that Idaho case law confirms charging fees doesn't make a nonprofit recreational use commercial, and that a welcome center and restrooms are ordinary accessory structures to a permitted park use.

January 20, 2026
BLP appeal denied by the commissioners

Only two commissioners, Ron Korn and Brian Domke, were present at the appeal hearing. Both voted to deny the appeal, following the county attorney Nate Adams's guidance.

January 20, 2026
Park designation lawsuit filed

With the county refusing to allow an appeal, PBR and PGS LLC filed a Petition for Judicial Review (Case No. CV09-26-0166), asking the court to overturn both the October 15 park-designation denial and the refusal to refer it to the Board as arbitrary, capricious, and unsupported by the record. The case was assigned to Judge McCrea.

Throughout 2025, into 2026, up until the injunction
Continuing to build out the ranch

Kept investing in the property the whole time, based on the county's approval of the donation model: new trails, new trailers, a third shuttle truck, well and septic work, and additional temporary facilities including a check-in building, storage, and bathrooms — right up until the injunction order, with the well and septic work still ongoing.

May 26, 2026
County posts a stop work order, no warning

After no violations since the August 2025 notice, the county posted a stop work order with no violation notices leading up to it.

June 15, 2026
Bonner County moves for an injunction

The county filed to halt operations pending the underlying park-designation case. Givens Pursley and Sandpoint Law step in, and the fight shifts to procedure — judicial notice disputes, a motion to dismiss the county's counterclaim, and a hearing that keeps getting reset.

June 30, 2026
First hearing before Judge McCrea

The county's evidence leaned on a gate and a since-removed "payment required" badge on the booking platform. The hearing went well but ran out of time and continued to the following week.

July 8, 2026
Second hearing — injunction granted

Felt like a strong showing after over an hour of witness testimony and argument, but the judge had an already-prepared bench decision, granted the county's injunction, and scolded PBR on several points. In her ruling, she also weighed in on the merits of the separate park-designation lawsuit — saying the facts presented "would tend to indicate" the property is more akin to a private club than a park — while stressing that wasn't a final finding and shouldn't be read as predicting who ultimately prevails. She directed both sides' attorneys to submit draft injunction language.

July 9, 2026
Dueling injunction drafts submitted

Both sides submitted competing proposed injunction orders — the county's sweeping and vague, PBR's narrower and tied to specific, enumerated activities.

July 16, 2026
Judge circulates her own draft order

Rather than adopt either side's proposed language, the judge circulated an unsigned draft with a "close personal relationship" carve-out for personal, non-commercial use — a term with no defined meaning in Idaho statute or county code. PBR's side views it as still too narrow. With no agreement reached, the court set a presentment hearing for July 31 to resolve the disputed language. Where the story stands today.